After concreting checks
1) All the flat portions of footings / underground structures shall be applied an epoxy based bituminous layer for protection against ground water.
Curing of shearwall , columns, slabs
Columns / Shear walls
1) Curing shall be done keeping the concrete surface wet by covering it with moist double Hessian cloth 2) Curing shall continue for at least 10 days.
Slabs
1) Curing of slabs shall be done as mentioned above.
2) Ponds shall be made within 24 hours of slab casting and till then slab shall be cured by spraying water.
3) Ponds shall be made at column locations first to cover from all sides and then to cover other portions of slab.
4) Care shall be taken to see to it that ponds are completely filled with water through out the recommended period for curing.
5) Vertical faces of the beams and area of slab out side ponds shall be cured by covering with wet Hessian cloth.
6) Incase where ponding is not done, whole slab should be covered with wet hessian cloth and care should be taken to keep it moist always.
1) Curing shall be done keeping the concrete surface wet by covering it with moist double Hessian cloth 2) Curing shall continue for at least 10 days.
Slabs
1) Curing of slabs shall be done as mentioned above.
2) Ponds shall be made within 24 hours of slab casting and till then slab shall be cured by spraying water.
3) Ponds shall be made at column locations first to cover from all sides and then to cover other portions of slab.
4) Care shall be taken to see to it that ponds are completely filled with water through out the recommended period for curing.
5) Vertical faces of the beams and area of slab out side ponds shall be cured by covering with wet Hessian cloth.
6) Incase where ponding is not done, whole slab should be covered with wet hessian cloth and care should be taken to keep it moist always.
Footings
1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.
2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces shall be cured similar to the columns.
1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.
2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces shall be cured similar to the columns.
How to protect fresh concrete
Protection of concrete
1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz: Hessian cloth, plastic sheets etc.
2) Concrete placed below the ground level shall be protected against contamination from falling earth, during placing.
3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent loss of mortar through walls.
4) Continuously dewatering the area through out the period of concreting and till initial set of concrete occurs with the help of dewatering pumps shall not be resorted to.
1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz: Hessian cloth, plastic sheets etc.
2) Concrete placed below the ground level shall be protected against contamination from falling earth, during placing.
3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent loss of mortar through walls.
4) Continuously dewatering the area through out the period of concreting and till initial set of concrete occurs with the help of dewatering pumps shall not be resorted to.
RCC - During Concrete checks
During Concreting Checks
1) Before starting concrete for the day, the gradation of fine and coarse aggregate shall be checked and if any deviation in combined gradation is observed, necessary corrections in
RMC (part4) - Ready Mix Concrete
On site the following information will be added:
-
(a) Time of arrival on site.
-
(b) Time when discharge was completed.
-
(c) Any water / admixture added by the supplier to meet the specified workability.
- (d) Any extra water or admixture added at the request of representative and his
RCC (part3 )- Ready Mix Concrete
slab pour self compacting concrete |
RCC (part2) Ready Mix concrete
hose pour slab |
-
3) Minimum Cement Content, Maximum Water Cement Ratio and Maximum Cement Content shall be as
per the requirements of IS 456:2000 with respect to the exposure conditions specified there in.
-
4) Site Engg requirement of workability at the pump point as measured by slump test shall be
between 140-160 mm, so that after pumping to the desired location the slump is minimum120 mm. Any
concrete shall be designed for a minimum three hours retention/open time. The workability of the
concrete shall be controlled on a continuous basis during production and any corrective action necessary
taken. No additional water, other than the amount required to produce the specified grade of concrete as
per mix design, shall be added to the truck mixer drum before discharge unless specifically requested
and signed for representative.
- Redosing or split dosing shall be allowed subject to the written permission of trained technicians and Engineers . In any case, the total dose should not exceed the maximum dose of admixture declared by Supplier or recommended by Admixture supplier. The supplier shall stock at least 50 litre of admixture with Quality Control department at site.
-
5) Any concrete poured should get finally set within maximum 24 hours.
-
6) Any concrete of a specified Grade shall meet the characteristic strength in 28 days. Any concrete being
supplied to our site, which does not achieve minimum characteristic strength at 28 days, shall be
considered as failure and no other acceptance criteria shall be entertained.
-
7) It is important to maintain the water cement ratio constant at its correct value. The amount of added
water shall be adjusted to compensate for any observed variations in the moisture contents in the
aggregates. Suitable adjustments should also be made in masses of the aggregates due to this variation.
Any change in water content due to change in aggregate grading shall be taken care of by forward
control by suitable modifications to mix design.
-
8) Batch sheets, moisture correction calculation/sheet shall be submitted along with challans for every pour
of concrete. The scope of addition of extra admixture (over and above the quantity which has already
been added at the time of batching at plant) shall be declared by concrete supplier. Immediately before
discharging the concrete at the point of delivery, the producer or his representative shall provide
Post Excavation Procedures
Post Excavation Procedures:
Antitermite Treatment to sides of excavated pits:
Antitermite Treatment to sides of excavated pits:
1) Antitermite treatment solution shall be prepared on site by mixing solution mentioned.
2) Antitermite treatment in foundation shall start after site Engineer gives his permission to do so. Treatment shall be complete with treatment of soil underneath the foundation as well as to the sides of the excavated pits to form a total barrier between foundation and excavated pits.
2) Antitermite treatment in foundation shall start after site Engineer gives his permission to do so. Treatment shall be complete with treatment of soil underneath the foundation as well as to the sides of the excavated pits to form a total barrier between foundation and excavated pits.
precaution to be taken blasting operation
Following precaution shall be taken blasting operation:
a) Area within minimum distance of 150m from the region to be blasted shall be evacuated. Boundaries of the
area to be blasted shall be guarded by minimum 4 persons who in turn shall wave red flags on the boundary to
prevent entry of personnel during blasting operation. Signal shall be given before and after blasting.
b) It shall be ensure that all charges have exploded by counting number of charges to fired and actual number of shots heard.
c) Misfires, if any, shall be brought to the notice of Consultant / Project Manager and necessary remedial measure shall be taken as per Consultant’s advice.
b) It shall be ensure that all charges have exploded by counting number of charges to fired and actual number of shots heard.
c) Misfires, if any, shall be brought to the notice of Consultant / Project Manager and necessary remedial measure shall be taken as per Consultant’s advice.
Important Points During Excavation Procedure
During Excavation Procedures:
1) The excavation shall be done to correct lines, dimensions and levels as per drawing. Adequate side slopes
shall be maintained during excavation of loose soil to prevent soil from sides of excavated pits from falling
back into the pits.
2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent sides of excavations from collapsing.
3) No heavy equipment shall be allowed within 6m from edge of excavation or within a distance equal to depth of excavation, whichever is less.
2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent sides of excavations from collapsing.
3) No heavy equipment shall be allowed within 6m from edge of excavation or within a distance equal to depth of excavation, whichever is less.
(part 2) procedure for EXCAVATION & BACKFILLING
shoring & strutting |
Excavation:
1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.
2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.
1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.
2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.
(how to) Procedures for Excavation and backfilling works including Antitermite Treatment
Procedures for Excavation and backfilling works including Antitermite Treatment
Pre Excavation Procedures:
Setting out:
1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.
Setting out:
1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.
(backfill) Storage of Raw Material
C) Storage of Raw Material
a) Soil for backfilling:
1) Excavated materials which in the opinion of Site Engineer are useful shall be stacked in regular heaps, bunds with regular slopes. Such stacking shall be done within the lead (50 m or as specified).
2) Stacks of soil shall be properly leveled for providing natural drainage.
1) Excavated materials which in the opinion of Site Engineer are useful shall be stacked in regular heaps, bunds with regular slopes. Such stacking shall be done within the lead (50 m or as specified).
2) Stacks of soil shall be properly leveled for providing natural drainage.
Guidelines for Inspection of Backfill Material
Even though hard murum is to be used as a back fill soil ideally, it should meet the following
Subscribe to:
Posts (Atom)