After concreting checks
1) All the flat portions of footings / underground structures shall be applied an epoxy based bituminous layer for protection against ground water.
Curing of shearwall , columns, slabs
Columns / Shear walls
1) Curing shall be done keeping the concrete surface wet by covering it with moist double Hessian cloth 2) Curing shall continue for at least 10 days.
Slabs
1) Curing of slabs shall be done as mentioned above.
2) Ponds shall be made within 24 hours of slab casting and till then slab shall be cured by spraying water.
3) Ponds shall be made at column locations first to cover from all sides and then to cover other portions of slab.
4) Care shall be taken to see to it that ponds are completely filled with water through out the recommended period for curing.
5) Vertical faces of the beams and area of slab out side ponds shall be cured by covering with wet Hessian cloth.
6) Incase where ponding is not done, whole slab should be covered with wet hessian cloth and care should be taken to keep it moist always.
1) Curing shall be done keeping the concrete surface wet by covering it with moist double Hessian cloth 2) Curing shall continue for at least 10 days.
Slabs
1) Curing of slabs shall be done as mentioned above.
2) Ponds shall be made within 24 hours of slab casting and till then slab shall be cured by spraying water.
3) Ponds shall be made at column locations first to cover from all sides and then to cover other portions of slab.
4) Care shall be taken to see to it that ponds are completely filled with water through out the recommended period for curing.
5) Vertical faces of the beams and area of slab out side ponds shall be cured by covering with wet Hessian cloth.
6) Incase where ponding is not done, whole slab should be covered with wet hessian cloth and care should be taken to keep it moist always.
Footings
1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.
2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces shall be cured similar to the columns.
1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.
2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces shall be cured similar to the columns.
How to protect fresh concrete
Protection of concrete
1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz: Hessian cloth, plastic sheets etc.
2) Concrete placed below the ground level shall be protected against contamination from falling earth, during placing.
3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent loss of mortar through walls.
4) Continuously dewatering the area through out the period of concreting and till initial set of concrete occurs with the help of dewatering pumps shall not be resorted to.
1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz: Hessian cloth, plastic sheets etc.
2) Concrete placed below the ground level shall be protected against contamination from falling earth, during placing.
3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent loss of mortar through walls.
4) Continuously dewatering the area through out the period of concreting and till initial set of concrete occurs with the help of dewatering pumps shall not be resorted to.
RCC - During Concrete checks
During Concreting Checks
1) Before starting concrete for the day, the gradation of fine and coarse aggregate shall be checked and if any deviation in combined gradation is observed, necessary corrections in
RCC (part3 )- Ready Mix Concrete
![]() |
| slab pour self compacting concrete |
RCC (part2) Ready Mix concrete
![]() |
| hose pour slab |
-
3) Minimum Cement Content, Maximum Water Cement Ratio and Maximum Cement Content shall be as
per the requirements of IS 456:2000 with respect to the exposure conditions specified there in.
-
4) Site Engg requirement of workability at the pump point as measured by slump test shall be
between 140-160 mm, so that after pumping to the desired location the slump is minimum120 mm. Any
concrete shall be designed for a minimum three hours retention/open time. The workability of the
concrete shall be controlled on a continuous basis during production and any corrective action necessary
taken. No additional water, other than the amount required to produce the specified grade of concrete as
per mix design, shall be added to the truck mixer drum before discharge unless specifically requested
and signed for representative.
- Redosing or split dosing shall be allowed subject to the written permission of trained technicians and Engineers . In any case, the total dose should not exceed the maximum dose of admixture declared by Supplier or recommended by Admixture supplier. The supplier shall stock at least 50 litre of admixture with Quality Control department at site.
-
5) Any concrete poured should get finally set within maximum 24 hours.
-
6) Any concrete of a specified Grade shall meet the characteristic strength in 28 days. Any concrete being
supplied to our site, which does not achieve minimum characteristic strength at 28 days, shall be
considered as failure and no other acceptance criteria shall be entertained.
-
7) It is important to maintain the water cement ratio constant at its correct value. The amount of added
water shall be adjusted to compensate for any observed variations in the moisture contents in the
aggregates. Suitable adjustments should also be made in masses of the aggregates due to this variation.
Any change in water content due to change in aggregate grading shall be taken care of by forward
control by suitable modifications to mix design.
-
8) Batch sheets, moisture correction calculation/sheet shall be submitted along with challans for every pour
of concrete. The scope of addition of extra admixture (over and above the quantity which has already
been added at the time of batching at plant) shall be declared by concrete supplier. Immediately before
discharging the concrete at the point of delivery, the producer or his representative shall provide