RCC (part 4) - Ready Mix Concrete


  1. 15)  All other requirements pertaining to Materials, Storage of Ingredients, production, delivery, batching equipments, quality control, sampling, order processing etc. as specified in IS 4926:2003 – “READY- MIXED CONCRETE-CODE OF PRACTICE” shall be binding on the producer / supplier of concrete.

Post Excavation Procedures


Post Excavation Procedures:

 Antitermite Treatment to sides of excavated pits:


1) Antitermite treatment solution shall be prepared on site by mixing solution mentioned.

2) Antitermite treatment in foundation shall start after site Engineer gives his permission to do so. Treatment shall be complete with treatment of soil underneath the foundation as well as to the sides of the excavated pits to form a total barrier between foundation and excavated pits.

(how to) Procedures for Excavation and backfilling works including Antitermite Treatment


Procedures for Excavation and backfilling works including Antitermite Treatment


Pre Excavation Procedures:


Setting out:

1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.