(part 2) procedure for EXCAVATION & BACKFILLING

shoring & strutting

Excavation:

1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.

2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.

(Part 1) Excavation and Backfilling with Antitermite Treatment


Raw Materials, their Inspection and Acceptance Criteria 

A) Soil used for backfilling:
JCB backhoe loader


1) Murrum: - Murrum for backfilling shall be freshly excavated, free from vegetation, boulders, silt and clay. Murrum can be either hard or soft.