(part 2) procedure for EXCAVATION & BACKFILLING

shoring & strutting

Excavation:

1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.

2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.

(how to) Procedures for Excavation and backfilling works including Antitermite Treatment


Procedures for Excavation and backfilling works including Antitermite Treatment


Pre Excavation Procedures:


Setting out:

1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.