Post Excavation Procedures
Post Excavation Procedures:
Antitermite Treatment to sides of excavated pits:
Antitermite Treatment to sides of excavated pits:
1) Antitermite treatment solution shall be prepared on site by mixing solution mentioned.
2) Antitermite treatment in foundation shall start after site Engineer gives his permission to do so. Treatment shall be complete with treatment of soil underneath the foundation as well as to the sides of the excavated pits to form a total barrier between foundation and excavated pits.
2) Antitermite treatment in foundation shall start after site Engineer gives his permission to do so. Treatment shall be complete with treatment of soil underneath the foundation as well as to the sides of the excavated pits to form a total barrier between foundation and excavated pits.
Important Points During Excavation Procedure
During Excavation Procedures:
1) The excavation shall be done to correct lines, dimensions and levels as per drawing. Adequate side slopes
shall be maintained during excavation of loose soil to prevent soil from sides of excavated pits from falling
back into the pits.
2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent sides of excavations from collapsing.
3) No heavy equipment shall be allowed within 6m from edge of excavation or within a distance equal to depth of excavation, whichever is less.
2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent sides of excavations from collapsing.
3) No heavy equipment shall be allowed within 6m from edge of excavation or within a distance equal to depth of excavation, whichever is less.
(part 2) procedure for EXCAVATION & BACKFILLING
| shoring & strutting |
Excavation:
1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.
2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.
1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.
2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.
(how to) Procedures for Excavation and backfilling works including Antitermite Treatment
Procedures for Excavation and backfilling works including Antitermite Treatment
Pre Excavation Procedures:
Setting out:
1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.
Setting out:
1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.
Guidelines for Inspection of Backfill Material
Even though hard murum is to be used as a back fill soil ideally, it should meet the following