Important Points During Excavation Procedure


During Excavation Procedures:



1) The excavation shall be done to correct lines, dimensions and levels as per drawing. Adequate side slopes shall be maintained during excavation of loose soil to prevent soil from sides of excavated pits from falling back into the pits.

2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent sides of excavations from collapsing.


3) No heavy equipment shall be allowed within 6m from edge of excavation or within a distance equal to depth of excavation, whichever is less.

(part 2) procedure for EXCAVATION & BACKFILLING

shoring & strutting

Excavation:

1) It shall be ensured that all necessary equipments, tools, instruments, material and consumables including temporary facilities like platform, walkways etc. as mentioned are available at site.

2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have sufficient experience on similar works.

(how to) Procedures for Excavation and backfilling works including Antitermite Treatment


Procedures for Excavation and backfilling works including Antitermite Treatment


Pre Excavation Procedures:


Setting out:

1) It shall be ensured that drawing indicating setting out points is available on site. Also necessary surveying equipment as mentioned shall be available on site in good operational condition.