Inspection of concrete after removal of formwork and Corrective Measures


1) On removal of formwork, the surface shall be examined by Engineer. The inspection shall
be carried out to check the finish of the concrete, deflections, bulges and other defects.

2) The corrective measures for the dimensional defects shall be taken in consultation with the structural consultant.


3) If any structural cracks are observed, they shall be brought to the notice of the structural consultant and shall be repaired at the earliest. 


4) In all cases 28 days cube strength shall be the basis for acceptance of concrete.

5) In case results of compressive strength of cubes show failure or low results than the acceptance criteria, the same shall be immediately reported to the structural consultant for initiating further course of action.


6) Structurally damaged members shall be brought to notice of Structural Consultant.
7) Certificate of Structural Consultant as regards safety of structure shall be obtained after each slab construction.


8) Breaking of structural member shall generally be avoided unless specifically asked by the Structural Consultant. 

3 comments:

  1. I like your articles, Good to see helpful information here, thanks lots for sharing.

    ReplyDelete
  2. Thank you for sharing your tips! This is very helpful and informative! I’m looking forward to seeing more updates from you.

    Elcometer

    ReplyDelete
  3. Thanks for sharing this post!
    Highly informative

    Elcometer

    ReplyDelete